Thursday, 20 November 2014

The Steps Involved in Developing a Wind Farm in Victoria

Wind farm development in Victoria requires careful planning and adherence to local regulations. Most of the wind farms take a considerable amount of time (5 years or more) from land negotiation to commissioning. The process of development starts with site identification, land negotiation, design, wind resource assessment, through wind farm planning approval in Victoria, financial close, then the construction phase and then its operation. The following write-up indicates the steps that are typically involved in developing a wind farm. Each step can be considered a hold point at which the decision to proceed to next step is made.

Step 1

Initial research (1st year)


The desktop study identifies the windy regions with potentially appropriate access, topography and environmental overlays, and feasible connection to the electricity grid.

Decision point: Find a landholder(s), commence negotiations.

Step 2

Getting in touch with the landholder, data gathering as well as constraint mapping (1st and 2nd year)


Short-term contracts are sought with the landlords to enable exclusive access to the properties for wind measurements, initial environmental studies, understanding the limitations and other such works. The agreements may include long-term lease options as well, which are to be activated when the project reaches the construction phase or step 7.

Decision point: Refine the design and continue with more in depth wind and environmental studies

Step 3

Refine the project area, complete environmental assessment (2nd and 3rd year)


The area where the wind farm is supposed to develop in Victoria is refined and a thorough landscape, environmental, noise and such other assessment studies are done. These inform the development of the draft management and building plans and, with the community input and landholder liaison, help identify the prospective locations for turbines, access tracks, electrical connection lines and other layout details of the project.

Decision point: Move on to the submission of the planning application and formal grid connection application

Step 4

The submission of development application development (3rd year)


A complete development application document is produced for consideration by the community and the suitable planning authorities in the statutory development assessment procedure. The assessment process gives everyone the chance to make formal submissions concerning the final application, prior to it being evaluated. This process of assessment can see the application approved with or without conditions or even refused.  In Victoria, planning regulations around wind farms may change over time depending on the State government attitude towards wind farms.

Decision point: The result of the application development process considered

Step 5

Wind turbine tenders and the final agreement for the grid connection (3rd and 4th year)


If the application is approved with conditions accepted, a contract is made with the electricity network for the future grid connection. Tenders are also sought for the turbines, balance of plant and construction.

Step 6

Financial Close: Making the investment decision (4th year)


Following the approvals as well as the tenders, the people planning to make the investment, then consider whether to make expenses for construction and operation of the wind farm. It generally involves investing 2- 2.5 million dollars per MW installed. The final decision of whether to proceed or wait depends upon several business and economic issues.

Decision point: To build or not to proceed.

Step 7

Wind Farm Construction (4th and 5th year)


If the decision is made is to move ahead with the construction, orders are to be placed for turbines and transformers at this stage. A construction company is also engaged in developing the wind farm in Victoria. Long-term agreements with the landholders are made and a Community Fund is created it is commenced.

Step 8

Generation (5th year)


The wind farm that has been developed in Victoria starts to generate electricity for the national grid.

Thursday, 18 September 2014

The Advantages of Wind Energy

We usually hear a lot about problems as well as alleged problems of wind energy in Victoria and much less about its advantages. The most essential point in favor of wind energy is that the electricity that’s generated replaces the power, which would otherwise be produced by burning the fossil fuels in Victoria. Thus, bigger the production of wind energy in electricity supply more is the reduction in production of atmospheric greenhouse gases, which cause ocean acidification and climate change.
 
However, a community where a wind farm is developed is benefitted by:
  • Business for the local contractors at the time of construction; transport, electrical, concreting etc
  • Employment at the time of construction and to a much less extent operation
  • A boost to the local businesses like motels, hotels and other kinds of accommodation providers, restaurants, cafes, gift shops, hardware shops etc; again especially at the time of construction and to a much less extent at the time of operation
  • Annual land lease payments to the farmers for turbine sites



Australia especially Victoria has a big potential for wind farm development. However, if this potential is to be built, governments should act more pro-actively. Apart from artificially created low price of the fossil fuel produced energy, the biggest hindrance to wind power development is lack of high capacity electricity transmission lines wherever they are required; and the governments are showing very little enthusiasm for building them. This should be compared with TX where state government is developing transmission lines into the areas with high quality resources of wind in hope of development of the wind farm.

Monday, 25 August 2014

The Wind Energy Services to Keep in Mind for Developing Wind Farms

The sector of wind energy is experiencing unexpected growth all over the world including Australia. Australia is a country where wind energy is highly ranked in Renewable Energy Country Attractiveness Index.  In fact, Large-scale Renewable Energy Target produces a financial motivation for growth and establishment of renewable energy power stations inspiring the main activity all over the board. With substantial wind resources, consistent environmental policy and extensive land areas, proper conditions exist in the country for the sector of wind energy to strengthen and expand.

For fulfilling its potential, the sector of wind power needs continued diligence in choosing and developing proper land areas with reliable resources, apt availability of equipment, wind turbine technology and controllable and safe power.

If you own a business in Victoria and its planning involves wind power generation for exporting energy at any distribution or for the transmission level in the country, you first need to realize the opportunity of your wind farm. While assessing this, you need to keep in your mind that there are a few services which would be of great value for your business. Mentioned below are those services:
  • Finding a site and acquiring wind farm prospects
  • Optimisation and design of wind farm
  • Wind farm planning approval in Victoria 
  • Visual evaluation of the wind turbine projects
  • Data analysis and monitoring of wind 
  • Assessment of noise of the wind energy projects 
  • Energy yield reporting, calculation and assessment 
  • Wind farms construction management 
  • Intervention of the environmental issues with regards to wind energy 
  • Market entry in the wind sector of Australia and forming partnerships within the country 
  • Capability statement for wind farm development 
  • Training of the staffs on wind power 
  • Shadow flicker evaluation of the wind farm

Tuesday, 22 July 2014

New South Wales Plans to be #1 in Energy and Environmental Policy

NSW aims to be the nation’s answer to California, speeding up the use of renewable energy and finding several ways for curbing waste, in a push which puts it at the odds with the coalition counterparts in the other states as well as at federal level. 

The Baird administration is of the opinion that it plans for adorning several of its buildings with the solar panels and ease the pathway to more of the wind farms. The message comes a few days after Abbott administration secured its 5 years quest to axe carbon price and along with the ongoing signs it may weaken the RET. 

Rob Stokes, the Environmental Minister, in a gathering in Sydney told that they are planning to make New South Wales #1 in environmental policy and energy. When it is about clean energy, they aim to be the nation’s answer to California, making a reference to the US state’s goal of achieving thirty-three percent of its power from the renewable sources within 2020 in comparison to twenty percent plus target of Australia. 

Investment in the large-scale renewable energy has all but slowed down in the nation with forty million dollars being spent in 2014’s first half or about 1.5 % of 2.67 billion dollars invested in 2013. The wind farm operators as well as all others are giving a warning that they’ll abandon Australian market for future investments if mandated requirement to supply 41,000 gigawatt-hours of the clean energy within 2020 is discarded. 

The Environmental Minister said that NSW was dedicated to 41,000 GW-h goal. Maverick MP Clive Palmer said that his party will be using the balance of power in Senate for blocking the effort by Abbott government for cutting the target of renewable energy. 

The Resource Efficiency Policy of NSW will take the benefit of administration’s scale to demand the savings. And according to Mr. Stokes, the investment over next decade may reach two hundred ninety million dollars and deliver savings to the energy bills of fifty-five million dollars every year.  All the new electrical gadgets bought by state should have to meet the average energy efficiency star rating for each and every gadget. The department of health will be needed to audit the energy use for fifty-five percent of their electric bills by the mid of the year in 2018; and other departments will need to audit forty percent of their billings. The rate is supposed to rise to ninety percent by 2024. 

In a completely different nod to renewable energy sector, the Environmental Minister said that he has suggested the Environment Protection Authority to treat the noise from the wind farms as this will offer certainty and clarity for the wind farm operators and may facilitate the right and responsible citing of the wind farms in the rural and regional areas. 

You can get more news, tips, advice and information about Australian wind farms, wind turbines in Australia, grant funding opportunities, how different kinds of renewable energy are used in Australia, wind energy in Victoria and other places by staying tuned to our blog.